Premises:
Warehouse of food and non-food products with an area of 23 thousand square meters.
Problem:
During the construction of the warehouse of food and non-food products, there was an uneven subsidence of the floor slabs and the foundation part of the landing stages.
During the survey, voids up to 15 cm were found under the floor slab, and the recorded deviation of the floor slab from the design mark reached 8 cm. The sediment of the foundation part of the landing stages was up to 9 cm, which led to the suspension of structures on neighboring elements.
Task:
Re-leveling the floor slabs in the horizontal plane, lifting the subsided elements of the foundation of the landing stages.
Decision:
GeoResin specialists performed work on strengthening the base of the floor slab, filling the detected spaces under the slab, leveling the floor slab in a horizontal plane, lifting the foundations of the decks and restoring the working condition of the landing stages.
Technological excessive subsidence of a building columns
Stopping subsidence and increasing the load-bearing capacity of the pile foundation
In a residential building, a floor slab sank after a pipe burst
Reinforcement of base soils and re-leveling of floor slab
Leakage of the retaining wall of the entrance to the underground garage
Compaction of soils and plugging of leaks in the retaining wall structure
Eroding the foundation of the supporting columns
Strengthening the foundation foundation without disrupting the entire project schedule
Reinforcement of foundation soils and stabilization of the foundation
Reinforcement of foundation soils and stabilization of the foundation
Strengthening the foundation soil and stabilizing the foundation
Strengthening the foundation soil and stabilizing the foundation
Subsidence of the slab and the appearance of a longitudinal crack
Compaction of the soil with filling the gap under the slab