Main task:
Strengthening of the foundation soil around the perimeter of a residential building. Based on the results of dynamic penetration test, we can conclude that there is a weak degree of compaction of the ground layers below the foundation level (Rd < 2.00 MPa) - insufficient load-bearing capacity
Data:
The house was built in 2014. Foundation – tape style; the mark of the sole of the foundation -3.0 m from the level of the day surface. The total area of the house is 180 m2 , including the ground floor. Gas block walls.
In 2017, the customer found small cracks on the facing brick. Initially, he assumed that the brick was of poor quality and decided to observe the changes and deformations. Later, cracks appeared on the inner sides of the basement walls, after which the customer immediately turned to GeoResin for advice.
Cracks were found in one half of the house, this part of the house (according to the customer's decision) we surveyed. The engineers gave recommendations for strengthening and surveyed the rest of the house.The client decided to continue monitoring, the drawdown continued and cracks appeared in the second part of the building. After conducting research, including a second survey to update the data and our proposal, a design solution was developed to increase the bearing capacity of the foundation ground.
Goal:
Strengthening the foundation soil at the base of the strip, eliminating uneven subsidence of the house.
Applied technology:
The solution to the problem was provided by the DEEP Lifting method according to the GeoResin technology. It includes measures to stabilize the foundation subsidence by strengthening and consolidating the soil in the base with increasing its strength and deformation characteristics with the GeoResin polymer composition. Strengthening of the foundation base was carried out to the depth of the stress distribution zone from the operating loads, ranging from -3.5 meters from the daytime ground surface to -5.7 meters.
Depending on the area of the injection, the packers were installed from one to three depth levels.
Result:
The work area was constantly monitored using a laser level during injections. To control the filling of voids and restore the load-bearing capacity, the technology provides a characteristic "movement" that indicates the achievement of the result. After the work was carried out, a geodetic survey was carried out to monitor the movements of the house during the warranty period.
Technological excessive subsidence of a building columns
Stopping subsidence and increasing the load-bearing capacity of the pile foundation
In a residential building, a floor slab sank after a pipe burst
Reinforcement of base soils and re-leveling of floor slab
Leakage of the retaining wall of the entrance to the underground garage
Compaction of soils and plugging of leaks in the retaining wall structure
Eroding the foundation of the supporting columns
Strengthening the foundation foundation without disrupting the entire project schedule
Reinforcement of foundation soils and stabilization of the foundation
Reinforcement of foundation soils and stabilization of the foundation
Strengthening the foundation soil and stabilizing the foundation
Strengthening the foundation soil and stabilizing the foundation
Subsidence of the slab and the appearance of a longitudinal crack
Compaction of the soil with filling the gap under the slab